This document presents the Construction Safety and Phasing Plan (CSPP) for the proposed rehabilitation of the runway at the Westover Field/Amador County Airport (Airport). This work is being performed under Federal Aviation Administration (FAA) Airport Improvement Program (AIP) Grant No. 3-06-0111-19. The anticipated construction duration is July 1, 2016 through October 30, 2016. Specifically, the Project scope includes the following elements:
Repair of pavement cracks by sealing or grinding existing runway pavement and replacing removed pavement.
Painting pavement striping and markings on the new pavement.
The objective of this CSPP is to provide a general outline of the construction safety and phasing provisions for working in or near the Air Operations Area (AOA) contained in the Contract Documents (Project Plans and Specifications), and to explain how those provisions will be implemented during construction.